Bucks Council releases its full roadworks schedule including carriageway schemes

Bucks Council has released its upcoming roadworks schedule for the following week.

Each week the authority releases a full works schedule of planned activity linked to its multi-million pound maintenance and improvement project.

Bucks Council’s full list does not include works overseen by utility companies or emergency closures.

Here is the full list for the week starting Monday:

Lots of road improvement work is plannedplaceholder image
Lots of road improvement work is planned

Carriageway Resurfacing

-A41 Bicester Road, Ludgershall (Monday 8 June to Friday 26 June) Carriageway resurfacing and other ancillary work will be carried out using a road closure, in operation between 19:00 and 07:00 (Monday to Friday only).

-Cock Lane, High Wycombe (Monday 15 to Wednesday 17 June) Plane and patch resurfacing works using a road closure in operation between 09:30 to 15:30.

-Quainton Road, Botolph Claydon (Tuesday 16 to Saturday 20 June) Plane and patch resurfacing works using a road closure in operation between 07:00 to 19:00.

Each week the council releases a list of planned roadworksplaceholder image
Each week the council releases a list of planned roadworks

-Kingsmead Road, High Wycombe (Thursday 18 to Friday 19 June) Plane and patch resurfacing works using a road closure in operation between 07:00 to 19:00.

Surface Dressing Preparation Works

-Marlow Road, Little Marlow (Monday 8 June to Monday 15 June) Targeted carriageway patching works in advance of the headline treatment taking place later in the summer; will be carried out using a road closure, in operation between 19:00- 07:00 (Monday to Friday).

Footway Structural Repairs

-Market Place, Chalfont St Peter (Tuesday 26 May to Friday 19 June) Footway reconstruction works will be carried out between 07:30 – 19:00, utilising temporary traffic signals in operation 24 hours.

-Thame Road, Haddenham (Monday 15 June to Saturday 22 August) Footway reconstruction works will be carried out between 09:00 – 15:00, utilising multiway traffic signals.

Bridge Maintenance

-Marlow Suspension Bridge (Monday 3 November 2025 to Tuesday 30 June 2026) Structural maintenance work ongoing with the bridge lowered on the new bearings on the south side of the bridge, and work will also continue on the South Pier. These activities will be carried out beneath the bridge.

To support the works, parking bays near Higginson Park and Pound Lane Car Park will be temporarily suspended for the duration of the project.

A road closure over the Bridge will be in place between 17 – 19 June 20:00 – 06:00.

-B4009 Grove Lane, Little Kimble (Tuesday 16 June) The sign replacement works will be carried out on the railway bridge using a road closure, in operation between 09:30 – 15:30.

-Abbey Way Flyover, High Wycombe (Monday 15 June to Friday 26 June) Leak mitigation will be carried out in Unit 68 of Abbey Way Flyover. These activities will be carried out below the bridge. No traffic management will be in place. Working hours 08:00 to 17:00.

Carriageway Coring Investigation Survey

-Vicarage Road and Verney Road, Winslow (Monday 15 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 09:30 – 15:30.

-Bushey Close, High Wycombe (Monday 15 June to Wednesday 17 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 08:00 – 18:00.

-Bailey Close, High Wycombe (Monday 15 June to Wednesday 17 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 08:00 – 18:00.

-Church Lane, Bledlow Ridge (Monday 15 June to Wednesday 17 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 08:00 – 18:00.

-Hamilton Road, High Wycombe (Tuesday 16 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 06:00 – 07:30.

-The Pastures, High Wycombe (Tuesday 16 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 09:30 – 15:30.

-The Drive, The Rise and The Green, Amersham (Tuesday 16 June to Thursday 18 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 08:00 – 18:00.

-Lansdowne Road, Chalfont St Peter (Tuesday 16 June to Thursday 18 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 08:00 – 18:00.

-Glebe Road, Chalfont St Peter (Tuesday 16 June to Thursday 18 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 08:00 – 18:00.

-Howe Drive & Netherwood Close, Knotty Green (Wednesday 17 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 09:30 – 15:30.

-Grenville Close, Burnham (Wednesday 17 June to Friday 19 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 08:00 – 18:00.

-Addington Estate Road, Addington (Thursday 18th June to Friday 19th June) Coring investigation survey in the carriageway using a road closure in operation between the hours of 09:30 – 15:30.

-Templewood Lane, Farnham Common (Thursday 18 June to Friday 19 June) Coring investigation survey in the carriageway using Two Way Temporary lights and Stop and Go Traffic Management in operation between the hours of 08:00 – 18:00.

-Stoke Common Road, Fulmer (Friday 19 June – Monday 22 June) Coring investigation survey in the carriageway using Give & Take and Short Delay Boards Traffic Management in operation between the hours of 09:30 – 15:30.

Vehicle Restraint Systems Works

-Park Lane, Lane End (Monday 1 to Tuesday 30 June) Safety barrier works using multi-way signals in operation 24/7.

Intelligent Transport Systems

-Camborne Avenue, Aylesbury (Thursday 18 June) Replacement of the toucan crossing push button units. No carriageway incursion or traffic management required.

Other Works

-Five points roundabout, Iver (From Monday 19 January to March 2027) Traffic management for Five Points Roundabout is a single lane 1 closure on Uxbridge Road west bound (exiting the roundabout.) and the lane 2 closure on Uxbridge road approaching the roundabout either side and the inner ring of the Five Points Roundabout, with two way traffic still flowing. No night works this week.