Seven Aylesbury projects included in council's latest roadworks schedule

Seven Aylesbury projects have been included in the council’s roadworks schedule this week.

Every week the authority releases an upcoming schedule of planned roadworks which will be carried out across the county.

This list focuses on works that are planned as part of the council’s year-round maintenance and improvement scheme.

Specific Aylesbury roadworks and wider county-wide projects have been included in this week’s list.

Each week the council releases a list of planned roadworksplaceholder image
Each week the council releases a list of planned roadworks

Bucks Council’s schedule does not include work overseen by utility companies and is subject to change at short notice.

Here is the full list:

Carriageway Resurfacing

-Vicarage Road & Verney Road, Winslow (Monday 17 August to Thursday 27 August)

Lots of road improvement work is plannedplaceholder image
Lots of road improvement work is planned

Carriageway surfacing will be carried out using a road closure, in operation between 7:30am and 7pm.

-Cam Mead, Aylesbury (Wednesday 26 August to Thursday 27 August)

Carriageway surfacing will be carried out using a road closure, in operation between 7:30am and 7pm.

-Long Meadow, Aylesbury (Friday 28 August to Friday 4 September)

Carriageway surfacing will be carried out using a road closure, in operation between 7:30am and 7pm.

Surface Dressing Headline Treatment

-Marsh Gibbon to Charndon Road / Charndon to Marsh Gibbon, Marsh Gibbon & Charndon (Tuesday 25 August)

The Lining and ironworks will be carried out using stop/go boards, in operation between 7am and 7pm.

-Edgcott Road / Marsh Gibbon Road, Marsh Gibbon & Grendon Underwood (Tuesday 25 August)

The lining and ironworks will be carried out using stop/go boards, in operation between 7am and 7pm.

-Iver Lane, Iver (Monday 24 August)

The lining and ironworks will be carried out using stop/go boards, in operation between 7am and 7pm.

-West Street, Steeple Claydon (Monday 24 August)

The Lining works will be carried out using a road closure, in operation between 8am and 5pm.

-Ledburn Road / Mentmore Road, Cheddington & Mentmore (Thursday 27 August)

The Lining and ironworks will be carried out using stop/go boards, in operation between 7am and 7pm.

-A4010 Wycombe Road, Saunderton (Monday 24 August to Tuesday 25 August)

The lining and ironworks will be carried out using a road closure, in operation between 8pm and 6am.

-Marlow Road, Little Marlow (Tuesday 25 August)

The lining and ironworks will be carried out using a road closure, in operation between 8pm and 6am.

-Lodge Hill, Dunsmore (Tuesday 25 August)

The surface dressing treatment will be carried out using a road closure, in operation between 7am and 7pm

-Mundaydean Ln, Marlow (Tuesday 25 August)

The surface dressing treatment will be carried out using a road closure, in operation between 7am and 7pm.

-Wash Hill, Wooburn Green (Tuesday 25 August)

The surface dressing treatment will be carried out using a road closure, in operation between 7am and 7pm.

-Village Road & Lake End Road, Dorney (Wednesday 26 August)

The surface dressing treatment will be carried out using a road closure, in operation between 7am and 7pm.

Drainage

-Chapel Lane, High Wycombe (Monday 10 August to Friday 28 August)

Installation of new outfall into watercourse and improve carriageway drainage, TM road closure, in operation 24/7 working hours between 7am and 7pm.

Footway Structural Repairs

-Wendover Way, Aylesbury (Monday 27 July to Saturday 29 August)

Footway reconstruction under a lane closure with traffic lights, work will be carried out between 7am and 7pm (Monday to Saturday).

-Cryers Hill Road, Cryers Hill (Wednesday 12 August to Saturday 12 September)

Footway reconstruction under a lane closure with traffic lights, work will be carried out between 7am and 7pm (Monday to Saturday).

Bridge Maintenance

-Marlow Suspension Bridge (Monday 3 November 2025 to Friday 11 September 2026)

Structural maintenance work is ongoing with the bridge lowered on the new bearings on the South side of the bridge, and work will also continue on the North Pier. These activities will be carried out beneath the bridge.

To support the works, parking bays near Higginson Park and Pound Lane Car Park will be temporarily suspended for the duration of the project.

-A412 Denham Road, Iver (Monday 3 August 2026 to Friday 28 August 2026)

Reconstruction of headwall and replacement of safety barrier. A 24-hour lane closure and two-way traffic lights will be in operation throughout the duration of the works including weekends. Working hours 7am to 7pm.

Carriageway Survey Works

-A41 Tring Road, Aylesbury (Monday 24 August to Thursday 27 August)

Carriageway survey works using Two way temporary lights and lane closure traffic management in operation between 8pm and 6am.

Street lighting

-County-wide damaged street lighting asset replacements (Monday 29 June to Wednesday 9 September)

As part of a multi-phase programme of street lighting improvements across Buckinghamshire, this programme of work will replace 40 damaged street lighting assets with new columns and energy-efficient LED lanterns.

The work will take place in Amersham, Aylesbury, Beaconsfield, Biddlesden, Bourne End, Buckingham, Calvert Green, Chesham, Fairford Leys, Flackwell Heath, Great Horwood, Hazlemere, High Wycombe, Marlow, Princes Risborough and Stoke Poges.

Lining Works

-School Keep Clear Road Markings (County-wide) (Monday 17 August to Friday 11 September)

As part of a countywide road-marking programme, School Keep Clear markings outside schools across Buckinghamshire will be refreshed.

School Keep Clear markings are the yellow zig-zag markings located outside school entrances, helping to keep the area clear of parked vehicles and maintain visibility for pedestrians and road users.

Works will take place at schools across Buckinghamshire during the summer holiday period to minimise disruption, including Aylesbury, High Wycombe, Chesham, Amersham, Beaconsfield, Wexham and various other schools across Buckinghamshire.

Traffic management measures will vary depending on the site, but the works will mainly be carried out overnight so disruptions will be limited.

-Capital Lining Refresh (Countywide) (Monday 17 August to Friday 16 October)

As part of a countywide road-marking programme across Buckinghamshire, worn road markings will be refreshed and reinstated where required to help maintain visibility and safety for all road users.

The programme includes the renewal of road markings such as centre lines, give way markings, road studs, high friction surfacing, lane markings and other carriageway markings that have deteriorated through normal wear and tear.

Works will take place at various locations across Buckinghamshire, including Aylesbury, Buckingham, Beachampton, High Wycombe, Wing, Amersham and various other highly frequented roads across the county.

Traffic management measures will vary depending on the site. Some road closures will be necessary to install the road-markings, however works will be carried out at night to avoid disruption where possible.

Other Works

-Five Points Roundabout, Iver (From Monday 19 January to March 2027)

Traffic management for Five Points Roundabout is a single lane 1 closure on Uxbridge Road west bound (existing the roundabout.) and lane 2 closure on Uxbridge Road approaching the roundabout, either side and the inner ring of the Five Points Roundabout, with two way traffic still flowing. Also temporary two-way lights on Wood Lane.