Digging begins in Aylesbury Vale on two of HS2’s longest cuttings

Enough rock and earth to fill the Royal Albert Hall more than 20 times needs to be excavated
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

HS2 Ltd has begun work on two of the longest cuttings on the new high-speed rail project, where the equivalent of more than 20 Royal Albert Halls’ worth of rock and earth must be excavated to provide a level bed for the railway.

Excavation has now started at the nearby Calvert cutting, which will take the line for 2.1 miles (3.4km) past Calvert Green and Steeple Claydon, roughly following the route of the disused Great Central Railway, which closed in the 1960s.

The cutting will take the line under four road bridges and the new East West Rail route, which is also currently under construction.

Excavation works at the Barton to Mixbury cutting, September 2022Excavation works at the Barton to Mixbury cutting, September 2022
Excavation works at the Barton to Mixbury cutting, September 2022

Around 685,000 cubic metres of material will be excavated to create the Calvert cutting, which will be up to 9.7m deep and wide enough to allow extra local railway lines to be added alongside the HS2 main line at a later date.

The two-and-a-half-mile (4.1km) Barton Hartshorn to Mixbury cutting, near Brackley, will be the project’s longest cutting, with 1.3 million cubic metres of material set to be excavated in stages over the next three years.

Running across the boundaries between Bucks and Oxon, the cutting will be up to 11m deep and will be crossed by six road, foot and bridleway bridges.

Material from the excavation – expected to be a mix of clay, sand, gravel and limestone – will be reused elsewhere on the project to help create embankments, noise barriers and landscaping. Sourcing these materials on site also helps to reduce the number of lorries on local roads.

Early work on the Calvert cuttingEarly work on the Calvert cutting
Early work on the Calvert cutting

HS2 Ltd’s project client, Rohan Perin, said: “Construction is now well under way across the whole first phase of the HS2 project, with almost 28,000 jobs now supported across the UK, and our initial earthworks made good progress over the summer.

"Some of the longest cuttings will be in Buckinghamshire and Oxfordshire, reducing noise and visual impact for local residents while carrying the new high-speed line under a series of road and railway bridges. It’s great to see a strong start to work on site.”

Construction of the two cuttings is being led by HS2’s main works contractor, EKFB – a joint venture between Eiffage, Kier, Ferrovial Construction and BAM Nuttall.

Deputy project director Dan Hockey said: “The earthworks at our longest cuttings are well under way and progress is steaming forward.

"While our works continue to progress, we have our local communities in mind and we’re continuously using our internal site access road to move people and materials around, reducing the impact on the local roads around our site areas.”

Other major cuttings, at Turweston in Northants, Waddesdon in Bucks, and Ladbroke, in south Warwickshire, are also well under way.

Across the 80km section of the HS2 route through Bucks, Oxon and West Northants, EKFB will need to shift approximately 36 million cubic metres of earth and rock over the next three years. About 99 per cent of this will be moved within HS2 land using a dedicated network of haul roads to reduce traffic on public roads.

In total, the first phase of HS2 will include 70 cuttings to keep the railway level as it crosses the countryside between London and Birmingham.

Related topics: