Here are the Aylesbury Vale roadworks affecting your journeys this week
During the course of this week Transport for Buckinghamshire will be carrying out work at the following locations as part of the Strategic Highway Maintenance Programme.
The works are part of a rolling programme of county-wide work. As some activities are weather dependent, dates may change at short notice.


No weekend working is planned.
Micro Surfacing Programme
Quarrendon Road and side roads, Amersham – various locations (Tuesday 27 October to Monday 3 November)
Carriageway Iron Works using a daytime road closure in operation between 7:00am and 7:00pm
Joint sealing Programme
Stratford Road, Thornborough - Foscote turn to Thornton turn (Wednesday 28 October to Thursday 29 October)
Carriageway Joint Sealing works using a night time road closure in operation between 7:00pm and 6:00am
Oxford Road, Stone - Roundabout at junction with Coldharbour Way (Friday 30 October)
Carriageway Joint Sealing works using a night time road closure in operation between 7:00pm and 6:00am
Bridge Improvement Programme
Ivy Lane, Great Brickhill - bridge adjacent to the Three Locks Golf Club to Heath Road (Monday 26 October to Friday 30 October)
Emergency Bridge Repairs using a road closure in operation 24/7
B488 Horton Road, Ivinghoe – 200m either side of the Grand Union Canal bridge (Monday 26 October to Friday 20 November)
Bridge Strengthening repairs using a 24 hour closure
Footway Structural Repair Programme
Cottesloe Road, Aylesbury – Churchill Avenue to Clover Lane (Monday 26 October to Friday 27 November)
Footway Improvement works using localised traffic management in operation between 7:30am and 4:30pm
London Road, Great Missenden - school playing field entrance to fire station (Monday 26 October to Friday 20 November)
Footway Improvement works using temporary traffic signals in operation between 9:30am and 3:30pm (3:00pm during school term time)
Drainage Improvement Schemes
Grovers Court, Princes Risborough - in cul-de-sac (Wednesday 28 October to Monday 3 November)
Drainage Improvement Works using localised traffic management in operation between 8:00am and 5:00pm
Missenden Road/Wey Lane/Church Street, Chesham ( Monday 26 October to Wednesday 23 December)
Installation of new culvert using a road closure in operation 24/7
Covid – Active Travel Plan
Southcourt , Aylesbury – various locations (Wednesday 28 October to Tuesday 10 November)
Pop up cycleway / Planters for point closures / lining works and additional signage using mobile works and temporary traffic signals in operation between 8:00am and 4:00pm
A40 London Road corridor improvements project
London Road, High Wycombe - Micklefield Junction (Friday 30 October)
Civil works / gully maintenance / lining works for Signal crossing upgrade using localised traffic management and lane closures (eastbound and westbound maintaining one lane open at all times) between 9:30am and 3:30pm